2 sets 230/63 kV substations in Kermanshah state
2 sets 230/63 kV substation in Babol and Minudasht cities
15 sets of 63/20 kV substation in three states
Turn key Project for 400/63 kV substation
Description : 63/20 kV , indoor S/S with hybrid PASS switchgear, and DCS control system (Montazere Ghaem yazd)Type: Turn key Client: Yazd REC.
63/20 kV substation with ABB Hybrid PASS Switchgear
Description : Double Circuit 63kV,transmission line between Bardasbi and KuhdashtType: TurnkeyClient: NIOEC (Ministry of Oil)
Description : Extension of 230kV substation Yazd II and Concerned Transmission lineType: TurnkeyClient: IPDC
Description : Ghaen 400 kV Power Plant Switchyard substationType: TurnkeyClient: IPDC
Description : 132/20 kV ,substation including two 30 MVA Transformers, two 132kV incoming and 5 outgoing 20kV feeder extendable up to 9 feederType: TurnkeyClient: Iran minerals production and supply Co.
Client: Gharb REC
Description : Voltage Adjustment of AmirKabir Dam Power Plant Substation From 132kV to 63kVType: Turnkey Client: Tehran REC
Description : Two sets complete 63/20 kV and Extension of Two sets 63/20kV substations for ZandjanType: Supplying Client: Zandjan REC
Description : Renovation of power network in Ahwaz oilfield siteType: Turnkey Client: South oilfield Co
Client: Khorasan REC
132 kV Double Circuit Transmission Line